December 2017 – 1.2 MW System

​Project Summary

TOTAL SIZE (DC)

​1.2 MW

​START DATE

​SEPTEMBER 28, 2017

​COMPLETION DATE

​DECember 11, 2017

​OFFTAKE STRUCTURE

​CDG

​NYSIO ZONE

​ZONE C

​Project Narrative

Renovus was contracted on September 28, 2017 to engineer, procure and construct a 1.2 MW solar system by the end of the year. To meet the construction deadlines, Renovus took the following actions: 

  • ​Evaluated the current work load of all sold work combined with the last minute addition of a project with a year-end deadline;
  • ​Instead of hiring temp labor, Renovus allocated one small but experienced team to the project;
  • ​Subcontractors were contacted and hired for fence installation, concrete pads, and some AC electrical work;
  • ​3,300 modules were installed in six days;
  • ​Renovus was able to combine sub-contractors with a small, 5-person crew to expedite installation;
  • ​By November 21st, the system was mechanically complete​. Interconnection was completed in December.