December 2017 – 1.2 MW System
Project Summary

TOTAL SIZE (DC)
1.2 MW

START DATE
SEPTEMBER 28, 2017

COMPLETION DATE
DECember 11, 2017

OFFTAKE STRUCTURE
CDG

NYSIO ZONE
ZONE C

Project Narrative
Renovus was contracted on September 28, 2017 to engineer, procure and construct a 1.2 MW solar system by the end of the year. To meet the construction deadlines, Renovus took the following actions:
- Evaluated the current work load of all sold work combined with the last minute addition of a project with a year-end deadline;
- Instead of hiring temp labor, Renovus allocated one small but experienced team to the project;
- Subcontractors were contacted and hired for fence installation, concrete pads, and some AC electrical work;
- 3,300 modules were installed in six days;
- Renovus was able to combine sub-contractors with a small, 5-person crew to expedite installation;
- By November 21st, the system was mechanically complete. Interconnection was completed in December.